17 & 17A Wilton Road · Builders' pack
REQUEST FOR QUOTATION · DRAFT

Ground-floor alterations: knock-through, new bathroom, and splitting 17 from 17A

17 & 17A Wilton Road, Salisbury SP2 7ED. The ground floor currently runs as one unit: a shop and old commercial kitchen at 17, and a flat at 17A. The works extend the 17A living room, add a bathroom, and build a proper boundary wall between the two properties.

Everything you need to price the job is on this page: the drawings, a numbered schedule of works, the bathroom specification with products, wall and floor build-ups, and site photos.

1. Drawings

GF-01 shows the layout today and GF-02 the proposal. The red numbers on GF-02 match the schedule of works below. Click either drawing to open the full A3 version.

GF-01 existing ground floor plan
GF-01 Existing ground floor. The ext space and old kitchen are open to each other today.
GF-02 proposed ground floor plan with numbered works
GF-02 Proposed ground floor. Numbered items 1–8 are listed in section 2.

Living-room revision 9: chimney breast and stair-access doorway added from the new photographs. Their dimensions and positions are approximate and must be measured on site. Other proposed works remain as previously drawn.

Key sizes

SpaceSize (m, internal)CeilingAfter the works
Living room (17A)4.00 × 3.722.42Knocked through into the ext space, ≈18.4 m²
Ext space2.45 wide × 3.25 deep2.26Front 1.30 m joins the living room; rear 1.80 m becomes the bathroom
Bathroom (new)2.45 × 1.802.26WC, basin, wudu basin, 1800 × 900 shower
Old kitchen (17)7.49 long, 0.83 → 2.36 wide (tapers)2.22Stays with 17; new wall along its 17A side
Store room4.36 × 2.202.30Split: 17A utility ≈2.45 × 2.20; 17 store ≈1.76 × 2.20
Shop (17)4.00 × 5.762.44–3.00No work
Sizes come from a phone scan (ARPlan app), averaged and squared up. Allow ±50 mm, and check every size on site before ordering or fabricating. Wall thicknesses (150 mm) and door positions are indicative. Rooms drawn dashed on the plans (17A hall, stairs, kitchen, conservatory, WC) have not been surveyed.

2. Schedule of works

Please price each item separately, using the same numbers. The bullets under each item show what we expect to be included.

  1. 1

    Knock-through: living room into the ext space

    Remove the rear wall of the living room across the full ext width (≈2.45 m opening).

    • Temporary support (props/needles). New beam or lintel and padstones to a structural engineer's design. Please include the engineer's calcs or state if excluded.
    • Building Control notice for the structural alteration.
    • Make good the floor, walls, ceiling and reveals. The floor levels and ceiling heights differ (2.42 against 2.26), so allow for a step or bulkhead and state how you'd finish it.
    • Existing door from the living room to the 17A kitchen stays.
  2. 2

    New partition forming the bathroom

    Stud wall across the ext, 1.80 m from the rear wall, giving an internal bathroom of ≈2.45 × 1.80.

    • Timber or metal stud with 50 mm mineral wool for sound. Moisture-resistant boarding (see section 4).
    • 700 mm internal door and frame from the living room, with a privacy lock and an undercut or vent for extract air.
  3. 3

    Bathroom fit-out

    Wet-room-style bathroom with a low-profile shower tray. Full specification in section 3.

    • Left to right: WC and small basin (by the existing waste pipe), frosted sliding divider, wudu basin, 1800 × 900 shower against the boundary wall.
    • Waste and water pipework, shower pump, extractor fan, lighting, wall panels, floor. See sections 3–5.
  4. 4

    New boundary wall along the ext (17 / 17A separation)

    Today the ext space is open to the old kitchen. Build a new full-height wall on the boundary line for the full ≈3.25 m length of the ext.

    • This wall separates two properties. Build it as a fire-separating wall (for example blockwork, or a stud wall with fire-rated board both sides and mineral wool) to Building Control's requirements.
    • Interim door ≈800 mm through this wall, just in front of the bathroom, so 17A and 17 stay connected for now. Price it as an FD30 fire door set with a self-closer, unless Building Control says otherwise.
  5. 5

    Carry the boundary wall through the store room

    Continue the same wall across the store room to the rear wall of the building.

    • The 17A side becomes a utility room (≈2.45 × 2.20). The 17 side keeps the store, the back door and the door to the WC.
    • Same fire-separating construction as item 4. Make good the ceiling and floor where they meet it.
  6. 6

    New doorway from the 17A conservatory into the utility room

    • Form the opening with a lintel. Door lining, architrave and a standard internal door.
    • Optional: price a washing-machine supply and waste in the utility room as a separate line.
  7. 7

    Rooflight over the knock-through

    ≈1000 × 800 rooflight in the existing flat roof over the front of the ext, to bring daylight into the living room.

    • Size to suit the joists: trimmers if any are cut. Kerb/upstand, flashing and making good the roof covering.
    • Plasterboard lining to the light well, and decoration.
    • Please report the condition of the flat roof, and price re-covering it as an option.
  8. 8

    Rooflight over the old kitchen

    ≈800 × 1100 rooflight in the flat roof over the wider rear half of the old kitchen. Same inclusions as item 7.

3. Bathroom specification

The layout follows the concept below, mirrored so the WC sits by the existing waste pipe. It is a compact, linear room with a walk-in shower, a wudu (ablution) basin, and a WC area behind a frosted sliding screen.

Concept visual of the finished bathroom: walk-in shower, wudu basin, frosted sliding door and WC with vanity basin
The finished bathroom (concept visual). On site the room is mirrored: WC and basin on the left, shower on the right against the boundary wall. The finishes, glass and fittings are as shown.

Layout (2.45 × 1.80, left to right)

  1. WC zone ≈0.85 m: WC against the back wall, facing the entrance side; small vanity basin opposite. Next to the existing waste pipe.
  2. Frosted sliding divider: separates the WC without a full cubicle.
  3. Entrance: 700 mm door from the living room.
  4. Wudu basin: on the back wall, next to the shower.
  5. Shower ≈0.90 m: 1800 × 900 tray running front to back, glass screen.

Ceiling height is about 2.26 m, which is low, so check the rain-head, extractor and light positions.

Fittings and products

ItemSpecificationNotes for the fitter
Shower traySydney low-profile rectangular stone resin tray, gloss white, 1800 × 900, with waste (Bathroom Mountain)Needs a flat, solid, level bed. Check you can get fall to the waste in the floor depth; chase into the slab or raise the tray if not.
Shower screenWalk-in clear glass panel, 8 mm, with wall profile and support barFix into studs or pattress, not board alone.
Shower valveThermostatic bar or concealed valve with rain head and slide rail / handsetMatch the valve to the pumped gravity supply (section 5).
Shower pump2-bar twin-impeller pump, positive or universal as the tank layout requiresHot water is gravity-fed: loft cold tank, cylinder and boiler. See section 5.
Wudu basinSiena Bathrooms Wudu Compact Duo: hand/face and foot-wash unit (Modern Living Direct)Hot and cold supply, and a waste run to the stack. Follow the maker's fixing heights. Heavy use means lots of splashing, so the wall behind needs full splash protection (section 4).
WCClose-coupled or back-to-wall compact WC with soft-close seatConnect to the existing soil/waste pipe on the left side. Confirm the pipe is a soil stack that can take a WC.
Vanity basinCompact floor-standing vanity unit with integrated basin and mixer tapOpposite the WC.
WC dividerFrosted (satin) glass sliding door on a top track, floor to about 2.0 mNo full cubicle. Fixed panel plus slider, fixed to a stud or pattress.
Wall finish10 mm Pietra Marble Ultra Matt shower panels (Easypanels) on all walls, floor to ceiling, with matching trims and approved adhesive/sealantInstall on the backing boards specified in section 4, following the panel maker's guide. Seal all joints and trims.
FloorSlip-resistant safety flooring (for example an Altro-type wet-area vinyl) coved 100–150 mm up the walls, over a tanked screedWater will reach the floor at the wudu basin, so treat the whole floor as a wet area, not just the shower.
ExtractorHumidistat or overrun fan, at least 15 l/s (Part F), ducted to outside through the wall or flat roofPlace it over the shower or wudu area. Door undercut for make-up air.
Lighting & electricsIP65 LED downlights on the zoned areas, mirror light, isolator for the fan and pumpPart P notifiable. RCD protection. Keep switches outside the room or use a pull cord.
ExtrasShower niche in the stud wall, towel rail, toilet roll holder, mirrorPlease price the towel rail (electric or plumbed) as an option.

4. Wall & floor build-up: what goes behind the splash panels

In short: standard plasterboard is not suitable anywhere in this bathroom. Use a cement-based or waterproof backer board ("aqua board") in the wet zones, and moisture-resistant (MR) plasterboard elsewhere.

AreaBackingWhy
Shower enclosure: both walls around the tray, full height, plus 300 mm past the end of the screenWaterproof backer board: cement board (e.g. Knauf Aquapanel / Hardie Backer) or XPS board (e.g. Marmox Multiboard), 12 mm. Joints taped and tanked with a liquid membrane kit, with tanking tape into the tray upstand.The wettest zone. If a panel joint or silicone line fails, the board and tanking keep water out of the studs. Plasterboard would soften and grow mould.
Wudu wall: behind and either side of the wudu basin, floor to ceilingSame as the shower: backer board plus tanking.Wudu involves a lot of splashing at low level (feet), several times a day.
WC and vanity wallsMoisture-resistant (MR, "green") plasterboard, 12.5 mm, is acceptable behind the Pietra panels. Tank the lowest 150 mm where the floor vinyl coves up.Splashes only, not direct water. The panels protect the face, and MR board resists humidity.
CeilingMR plasterboard with a bathroom-grade paint, or a matching ceiling panelHumidity only. Vapour check over it if the flat roof above is cold.
Existing masonry walls (rear, 17A kitchen side)Find and fix the cause of the damp first. Then treat the mould and fix backer or MR board on treated battens or with adhesive dabs.The photos show damp and black mould on the old walls. Panels over untreated damp will fail.
FloorLevel screed, then a liquid tanking membrane over the whole floor, up the walls 150 mm, then safety vinylWater from the wudu area reaches the floor, so the whole floor must be watertight.
Is plasterboard enough? Behind waterproof panels, MR plasterboard is fine for the WC and vanity walls. In the shower and at the wudu basin, use a cement or waterproof backer board and tank it. It costs little extra, and it's where bathrooms fail. Always check the panel maker's fitting guide, as their warranty may name approved substrates.

5. Water supply & services

What's there now

  • A gravity-fed hot water system: a large cold-water tank in the loft; a smaller cold tank on the first floor, above the hot-water cylinder; and a boiler.
  • A large existing waste/soil pipe on the left side of the ext, where the WC is planned. Its size and route aren't confirmed.
  • No mains-pressure hot water, so a shower pump is needed.

Please confirm and price

  • Pump type and position: a 2-bar twin pump, and whether the cylinder needs a dedicated shower feed (e.g. a Surrey or Essex flange).
  • Whether the existing waste pipe can take the WC, plus the wudu, basin and shower wastes with proper falls.
  • Hot and cold runs to the ground-floor bathroom from the cylinder and tank.
  • Extractor duct route out through the wall or the flat roof.
  • Electrics: new circuit or spur for the pump, fan and lights, with Part P certification.

6. Site photos (27 September 2026, during strip-out)

The old commercial kitchen and ext space. Equipment is still in place and will be removed. Wall linings are partly stripped.

Old kitchen with range, sink and shelving; glazed external door on the left, boarded recess under a lintel in the centre, brown door and pipe on the right
Old kitchen: glazed external door (left), boarded recess under a lintel (centre), brown door and pipe (right).
View across the kitchen towards the brown door and pipe, with stripped wall linings
Looking towards the brown door. Stripped linings and damp staining.
Close-up of a boarded recess with timber battens under a concrete lintel, part-tiled below
Boarded recess under a lintel. Its purpose is to be confirmed on site.
Wall with black mould and damp staining next to a large vertical pipe and a brown door
Damp and black mould at low level; a large vertical pipe next to the door.
Plywood-lined walls with pencil height marks and a mouldy corner, glazed door on the left
Plywood-lined walls with height marks (≈2.28–2.31 m) and a damp corner.
Wide view of the boarded recess, tiled splashback, sink and stripped walls
Wider view of the recess wall and existing sink position.

More photos and a 3D walkthrough of the existing layout are on the main page.

7. How to quote

Please include

  • A price for each item 1–8, split into labour and materials.
  • For the bathroom (item 3): supply and fit, and separately fit only, in case we supply the tray, wudu unit and panels ourselves.
  • Structural engineer, Building Control fees and electrical certification: included, or listed as excluded.
  • Strip-out of the old kitchen equipment and waste disposal (skip).
  • Programme: how many weeks, the order of work, and when the bathroom is usable.
  • Any assumptions, provisional sums, and anything you think we've missed.

Please check on your visit

  • All key sizes (the drawings come from a phone scan).
  • The wall to be knocked through: is it load-bearing, and what does it carry?
  • Floor levels and slab depth for the tray waste and the wudu waste falls.
  • The existing waste pipe: is it a soil stack, what size, and where does it run?
  • Flat roof joist direction and spacing, and the condition of the covering at both rooflight positions.
  • The cause of the damp on the old walls.
These are draft drawings for discussion and pricing, not for construction. Structural design, Building Regulations approval (structure, fire separation, drainage, ventilation, electrics, rooflight thermal performance) and any Party Wall matters must be confirmed before work starts.